Introduction:
Production capacity estimation for a garment factory is an important issue in ready made garments sector. It plays an important role to the buyer for selecting right vendor for their orders. How much a garment factory can produce their items per day has estimated here. As its importance in garments manufacturing sector, today I will present here the production capacity estimation method for a garment factory.
Production Capacity:
Production capacity of a garment factory is totally related with machine (hr) capacity, line efficiency of that factory and standard allowed minute (SAM) of produced item. For achieving accurate production capacity of a garment factory, an industrial engineer should confirm accurate cutting room capacity, finishing room capacity and washing capacity also.
Production Capacity Calculation Method of a Garment Factory:
For calculating production capacity of a garment factory, an industrial engineer should confirm the below information:
- Machine (hr) capacity per day,
- Individual product’s standard allowed minute (SAM),
- Line efficiency of garment factory or factory efficiency.
Now, by using the following formula, an industrial engineer can easily calculate production capacity of a garment factory.
Production capacity (Pcs),
Example:
Suppose, Noman Fashion Ltd. has 10 sewing lines, each sewing line has 20 machines. They have to produce basic knitted polo shirt items at 8hrs working day, (where machine-hr capacity is 1600hrs and line efficiency is 60%).
So, find out the production capacity of that factory.
Solution:
Here,
Machine (hr) capacity per day= 1600hrs,
Line efficiency of garment factory= 60%,
Standard allowed minute (SAM) for knitted polo shirt= 20
So,
Production capacity (Pcs),
= 2880pcs
= 2880pcs
So, garments production capacity of the above factory is 2880 pcs per day.